FAQ Topic: Planning Review Process

Large Home Projects – Planning Commission Design Review (+/- 90 Days)

Large-sized home projects require Planning Commission Design Review. The approval process usually takes about 90 days. However, this can take longer depending on the complexity of the project and the impact it will have on the neighborhood. Large home projects are typically characterized as: Location and Design of all significant remodels and new structures. Construction or installation of new fences, … Continued

Medium Home Projects – Planning Staff Design Review (+/- 50 Days)

Medium-sized home projects may only require Planning Staff Design Review. The approval process usually takes about +/- 50 days. Medium home projects are typically characterized as: Interior remodels of any size. Minor additions, extensions or exterior changes to, or reconstruction of existing dwellings and related accessory structures. Minor changes to exterior materials or colors that significantly alter the appearance … Continued

Small Home Projects – Exempt from Design Review (1-2 Days)

Small-sized home projects are often subject to Design Review Exemption. The determination and approval process usually takes 1-2 Days. Small-sized home projects are typically characterized as: Most replacement and repairs including roofing, windows, and siding. Minor exterior color or material changes including paint, roof, and siding material when consistent with the provisions of chapter 20.04.140. Landscape changes or … Continued

Close window